MANUFACTURING QUALITY CHART



COMPILED BY TEAM MEMBER 2
TEAM MEMBER 3 TEAM MEMBER 4
SUPPLIER Webroy (Pty) Ltd MQC No
CUSTOMER REV No.
PART NAME DATE INITIATED
PART No. REVISION DATE 2024/08/28
    LAST REVIEW DATE 
WEBROY STOCK CODE STATUS
MANUFACTURING LOCATION Webroy SAFETY CRITICAL
MQC TYPE
Current
Process Flow Key

Process TypeImage
PARTS STOCK
COMPONENT PART
PROCESS OPERATION
SAMPLING INSPECTION
100% INSPECTION
TRANSPORT
Responsible
Confirmation Level Key
NameImage
OPER
T/L
SUPERVISOR
MNGR
OPER
T/L
SUPERVISOR
MNGR


PROCESS FLOWNONAMEWORK ELEMENTCHECK ITEMRANKPROCESS CRITERIONINSPECTION METHODINSPECTION PLANFREQUENCYInspection No.(s)Work InstructionsRESPCHECK SHEETCONFIRM'N LEVELREACTION PLAN 
1Receiving 6.00 mm Ferrule - Stores PersonelReceiving6.00 mm ferrule Check for correct quantity delivered and size.Visual inspection and verification as per orderDelivery note and orderEvery batch 1090
Goods receive note book / delivery note Should there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D
2Inspection of 6.00 mm Ferrule by Q.C.Inspection6.00 mm ferrule SC No damage, distortion or burrs. Dimple must be present and centralized. Wire must fit in freely.Visual inspectionMeasure 5 components per batch.Every batch 20446
Record on inspection sytem. Any non-conforming ferrules shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator
3Receiving raw material - Stores PersonnelReceivingRaw material Check for correct quantity delivered, type and diameter.Visual inspection and verification as per orderDelivery note and orderEvery batch 1090
Goods receive note book / delivery note Should there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D
4Move material to receiving storage areaTransportRaw material Store material correctlyVisual inspectionAs per FIFO systemEvery batch Visual inspection If difficulty occurs in storing raw material properly inform Stores Coordinator
5Inspection of raw material by QA personnelInspectionRaw material SC Spring steel wire. EN10204. WIRE/SBS3/0290. Correct diameter 2.90mm +/- 0.025. Correct tensile 1373 Mpa - 1618 Mpa. No score marks, no rust on wire.Visual inspection, MicrometerAs per incoming raw material inspection QD207Every consignment 6216
1120
Goods receive notebook / Buff tag and record findings on electronic sytem Any non-conforming raw material shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator
6Move raw material to dedicated area for storageTransportRaw material Safe stacking of wire coils as per allocated areas and FIFO systemVisual inspectionAs per FIFO systemOn receiving Identification tags Any difficulty experienced during this activity report to Stores Coordinator
7Issue wire to productionIssuingRaw material Issue wire to productionVerification as per buff tag Setter to measure wire diameter with vernierEvery coil issued to production.Every job as per request Route card Should the incorrect wire be issued to production stop process, correct and inform Stores Coordinator
8Form wireFormingWire SC Wire shall conform to drawing and wire profile must comply to checking fixture, Wire must be flat. Leg lengths must be correct on checking fixture. No rust, Score Marks and Burrs. Visual Inspection and measure length with a tape measure. First-off verification by Q.AAs per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 17436
17437
17438
1213
Record on Electronic system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor
9Transport wire to crimping pressTransportWire Correct handling of parts during this activityVisual verificationN/AEvery order N/A Any difficulty experienced during this activity stop the process and report to Supervisor
10Assemble ferruleAssemblyCompleted parts Crimping of ferrulePart to meet drawing and customer requirements. Wire ends must be meet ferrule dimple to ensure correct crimping. Ferrule must be assembled/ crimped securely - Refer CAR 53441.Visual verificationEvery part 1214
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor
11Inspect part in final checking fixtureInspectionCompleted parts SC Part shall sit flat and comply to checking fixture. Ferrule to be crimped securely. No rust, burrs, damage or distortion.Visual inspection refer to work instruction for fitment requirements.Visual verification in checking fixture for correct fitment & assembly.First-off at start of production. In-process 9 parts every hour and last-off 11382
11383
11384
1214
Record on inspection system Should the inspection requirements not be correct, stop the process and inform the supervisor.
12Pack assembled parts into binsPackingCompleted parts Correct quantity = 500 parts per bin. Bin type: 4116Visual verificationAs per packaging specificationEvery order F.A Card Should the quantity be incorrect, stop process, verify quantity and add/remove products to meet quantity required
13Transport completed parts to stores for dispatchTransportCompleted parts Correct quantitiesVisual inspectionAs per job orderEvery order N/A Should difficulty occur during transport inform Supervisor
14Receipt parts into stockReceiptingCompleted parts Correct quantity to be entered on to the stock systemVisual verification.Every batch.Every order 1094
F.A Card. Any discrepancies shall be reported to the Stores Coordinator
15Dispatching of productsTransportCompleted parts Bin type: 4116, QTY: 500 per binVisual verificationAs per job orderEvery order 1101
Delivery note / invoice Any difficulty experienced during this activity report to Stores Coordinator
16Layout functional inspectionInspectionParts Full dimensional as per SDS and PIS.As per customer requirements.1 complete productAs per schedule Audit sheet Should the audit fail, the Production manager shall be informed immediately.