MANUFACTURING QUALITY CHART



COMPILED BY TEAM MEMBER 2
TEAM MEMBER 3 TEAM MEMBER 4
SUPPLIER Webroy (Pty) Ltd MQC No
CUSTOMER REV No.
PART NAME DATE INITIATED
PART No. REVISION DATE 2023/11/03
    LAST REVIEW DATE 
WEBROY STOCK CODE STATUS
MANUFACTURING LOCATION Webroy SAFETY CRITICAL
MQC TYPE
Current
Process Flow Key

Process TypeImage
PARTS STOCK
COMPONENT PART
PROCESS OPERATION
SAMPLING INSPECTION
100% INSPECTION
TRANSPORT
Responsible
Confirmation Level Key
NameImage
OPER
T/L
SUPERVISOR
MNGR
OPER
T/L
SUPERVISOR
MNGR


PROCESS FLOWNONAMEWORK ELEMENTCHECK ITEMRANKPROCESS CRITERIONINSPECTION METHODINSPECTION PLANFREQUENCYInspection No.(s)Work InstructionsRESPCHECK SHEETCONFIRM'N LEVELREACTION PLAN 
1Receiving raw material - Stores PersonnelReceivingRaw material Check for correct quantity delivered, type, Diameter. Check for COAVisual verification and verification as per orderVisual inspection and verification as per orderEvery batch 1090
Goods receive note book / delivery note Should there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D
2Move raw material to incoming inspection areaTransportRaw material Store material properly in baysVisual verificationAs per FIFO systemEvery batch Visual inspection If difficulty occurs in storing raw material properly inform Stores Coordinator
3Raw material incoming inspection by QA PersonnelInspectionRaw material SC Correct Ø - 6.00 mm ± 0.08 mm. Correct type - SWM - B. Tensile range 550mpa - 750mpa. No rusty wire. No score marks. No excessive drawing soapVisual inspection and measure with a MicrometerAs per incoming raw material inspection planEvery batch 6180
1120
Goods receive notebook / Buff tag and record findings on electronic sytem Any non-conforming raw material shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator
4Move wire to storage area for safe stackingTransportRaw material Safe stacking of wire coils onto racks as per allocated areas and FIFO systemVisual verificationAs per FIFO systemOn receiving Identification tags Any difficulty experienced during this activity report to Stores Coordinator
5Issue raw material to Production PersonnelIssuingRaw material Correct wire to be issued as per route cardVerification against buff tagEvery coil issued to productionEvery job as per request 1080
Route card Should the incorrect wire be issued to production stop process, correct and inform Stores Coordinator
6Straighten wire and cut to lengthCut to lengthsBox wire SC Correct cut length - 373.00 mm ±1.00 mmVisual inspection and tape measure - As per work instruction no. 1224As per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 21488
21489
21490
21488
21489
21490
1224
1224
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor
7Move straight cut wire to wire benderTransportIndivual Wires Safe transportation of wiresVisual verificationN/AEvery order N/A Any difficulty experienced during this activity stop the process and report to Team leader
8Form loop wire on 12mm Huron MachineFormingLoop wire SC Wire shall conform to checking fixture , wire to sit flat in grooves on fixture to prevent fitment issues - refer CAR 45328Visual inspection and checking fixture - As per work instruction no. 1225As per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 21491
21492
21493
1225
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Team leader
9Move loop wire to spot welderTransportIndivual Wires Safe transportation of wiresVisual verificationN/AEvery order N/A Any difficulty experienced during this activity stop the process and report to Team leader
10Form straight cut wire on wire benderFormingBox wire SC Wire shall conform to checking fixture , wire to sit flat in grooves on fixture to prevent fitment issues.Visual inspection and checking fixture - As per work instruction no. 1226As per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 21494
21495
21496
1226
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Team leader
11Move formed wires to spot welderTransportIndivual Wires Safe transportation of wiresVisual verificationN/AEvery order N/A Any difficulty experienced during this activity stop the process and report to Team leader
12Assemble and spot weld wiresWeldingWelded part SC Part must conform to drawing requirements Visual inspection and checking fixture - As per work instruction no. 1054As per work instructionEvery part 21497
21498
21499
1227
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Team leader
13Inspection of welded componentInspectionWelded part in checking fixture SC Part must conform to drawing and checking fixture requirements. Sufficient weld penetration - material thickness on spot welded area should be 10.25 mm ±0.25 mm.100% inspection on final checking fixtureAs per work instructionEvery part 21497
21498
21499
1227
Record on inspection system Should the inspection requirements not be correct, stop the process and inform the Team leader
14Pack welded components in binsPackingWelded parts Correct quantities, correct packaging methodVisual verificationAs per packaging specificationEvery batch F.A Card Should the quantity be incorrect, stop process, verify quantity and add/remove products to meet quantity required
15Transport welded components to storesTransportWelded parts Correct quantities as per F.A cardVisual verificationAs per job orderEvery order N/A Should difficulty occur during transport inform Team leader
16Receipt of components ReceiptingCompleted parts Correct quantity to be entered on to the stock systemVisual verification against F.A cardEvery batchEvery order 1094
F.A Card Any discrepancies shall be reported to the Stores Coordinator
17Dispatching of productsTransportCompleted parts Bin type: 4622, QTY: 60 per binVisual verificationAs per job orderEvery order 1101
Delivery note/ invoice Any difficulty experienced during this activity report to Stores Coordinator
18Layout functional inspectionInspectionParts Full dimensional as per SDS and PIS.As per customer requirements1 complete productAs per schedule Audit sheet Should the audit fail, the Production manager shall be informed immediately