MANUFACTURING QUALITY CHART



COMPILED BY TEAM MEMBER 2
TEAM MEMBER 3 TEAM MEMBER 4
SUPPLIER Webroy (Pty) Ltd MQC No
CUSTOMER REV No.
PART NAME DATE INITIATED
PART No. REVISION DATE 2024/05/22
    LAST REVIEW DATE 
WEBROY STOCK CODE STATUS
MANUFACTURING LOCATION Webroy SAFETY CRITICAL
MQC TYPE
Current
Process Flow Key

Process TypeImage
PARTS STOCK
COMPONENT PART
PROCESS OPERATION
SAMPLING INSPECTION
100% INSPECTION
TRANSPORT
Responsible
Confirmation Level Key
NameImage
OPER
T/L
SUPERVISOR
MNGR
OPER
T/L
SUPERVISOR
MNGR
Isringhausen


PROCESS FLOWNONAMEWORK ELEMENTCHECK ITEMRANKPROCESS CRITERIONINSPECTION METHODINSPECTION PLANFREQUENCYInspection No.(s)Work InstructionsRESPCHECK SHEETCONFIRM'N LEVELREACTION PLAN 
1Receiving raw material - Stores PersonnelReceivingRaw material Check for correct quantity delivered, type, Diameter. Check for COAVisual verification and verification as per orderDelivery note and orderEvery batch 1090
Goods receive note book / delivery note Should there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D
2Move raw material to incoming inspection areaTransportRaw material Store material properly in baysVisual verificationAs per FIFO systemEvery batch Visual inspection If difficulty occurs in storing raw material properly inform Stores Coordinator
3Raw material incoming inspection by QA PersonnelInspectionRaw material SC Correct Ø - 6.50 mm ± 0.06 mm. Correct type - Spring black wire. Tensile range 1380mpa - 1550mpa. No rusty wire. No score marks. No excessive drawing soapVisual inspection and measure with a MicrometerAs per online incoming raw material inspection planEvery consignment 6178
1120
Goods receive notebook/ Buff tag and record findings on system Any non-conforming raw material shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator
4Move wire to storage area for safe stackingTransportRaw material Safe stacking of wire coils onto racks as per allocated areas and FIFO systemVisual verificationAs per FIFO systemOn receiving Identification tags Any difficulty experienced during this activity report to Stores Coordinator
5Issue raw material to Production PersonnelIssuingRaw material Correct wire to be issued as per route cardVerification against buff tagEvery coil issued to production.Every job as per request 1080
Route card Should the incorrect wire be issued to production stop process, correct and inform Stores Manager
6Straighten wire and cut to lengthStraighten and cut to lengthsProduct SC Correct cut length - 550.00 mm ±1.00 mmVisual inspection and tape measure As per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off



Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor
7Move straight cut wire to wire benderTransportProduct Safe transportation of wiresVisual verificationN/AEvery order N/A Any difficulty experienced during this activity stop the process and report to Supervisor
8Form bend 1 on hand benderFormingProduct SC Component shall conform to checking fixture, component to fit profile correctly on fixture to prevent fitment issuesVisual inspection and checking fixtureAs per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 1176
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervison
9Form bend 2 on hand benderFormingProduct SC Component shall conform to checking fixture, component to fit profile correctly on fixture to prevent fitment issuesVisual inspection and checking fixtureAs per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 1176
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor
10Form radiusFormingProduct SC Component shall conform to checking fixture, component to fit profile correctly on fixture to prevent fitment issuesVisual inspection and checking fixtureAs per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 1176
Record on inspection system Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor
11LTHT of torsion barLTHTProduct 240 °C for 30 minsVisual verification. Record on heat treatment log sheet (QD:52)Visual inspection temperature.Every batch Record oven temperature on QD:52 Any difficulty experienced during this activity stop the process and report to supervisor.
12Final inspection of torsion barInspectionCompleted products Component shall conform to customer/ drawing requirements. Bend 1 length: 30.00 mm ±2.00 mm, bend 3 length: 63.00 mm ±2.00 mm, Correct overall length: 375.00 mm ±2.00 mm - Refer CAR 52420. No burrs/ sharp edges & correct fitment on checking fixtureChecking fixture, vernier and visual verificationAs per work instructionEvery batch 10362
10363
10364
1176
Record on inspection system Should the inspection requirements not be correct, stop the process and inform the Supervisor
13Transport completed components to stores.TransportCompleted products Safe loading and transporting of components.Visual inspection.As per job orderEvery order N/A Should difficulty occur during transport inform Supervisor
14Receipt of componentsReceiptingCompleted parts Correct quantity to be entered on to the stock systemVisual verification against F.A cardCross off the F/A card to indicate it has been received on the system.Every batch 1094
F.A Card Any discrepancies shall be reported to the Stores Manager
15Despatching of components.TransportCompleted products Safe handling during this activity.Verification of quantities as per sales order and delivery note.As per job orderEvery order 1101
Delivery note / invoice Any difficulty experienced during this activity report to Stores Coordinator
16Internal product audit.InspectionCompleted products As per drawing and audit requirements.Competent Q.A personnel conducting inspections.1 complete productAs per schedule 1180
Audit sheet Should the audit fail, the Production manager shall be informed immediately.