| PROCESS FLOW | NO | NAME | WORK ELEMENT | CHECK ITEM | RANK | PROCESS CRITERION | INSPECTION METHOD | INSPECTION PLAN | FREQUENCY | Inspection No.(s) | Work Instructions | RESP | CHECK SHEET | CONFIRM'N LEVEL | REACTION PLAN | |
| 1 | Receiving raw material - Stores Personnel | Receiving | Raw material |
| Check for correct quantity delivered, type and diameter. | Visual inspection and verification as per order | Check for correct quantity delivered, type and diameter. | Every batch |
|
1090
|
| Goods receive note book / delivery note |
| Should there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D |
|
| 2 | Inspection of raw material by QA personnel. | Inspection | Raw material |
| Mild black wire. WIRE/MBH2/0500. Correct diameter 5mm +/- 0.08. Correct tensile - 500mpa to 750mpa.No score marks, no rust on wire. | Visual inspection, Micrometer | Mild black wire. SAE 1010/1008. Correct diameter Correct tensile - 500mpa to 700mpa.WIRE/MBH2/0500. Correct diameter 5mm +/- 0.08. Correct tensile - 500mpa to 750mpa.No score marks, no rust on wire. | Every batch |
6179
|
1120
|
| Goods receive notebook / Buff tag and record findings on electronic sytem |
| Any non-conforming raw material shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator |
|
| 3 | Move material to dedicated area for storage. | Transport | Raw material |
| Safe stacking of wire coils as per allocated areas and FIFO system. | Visual inspection. | Safe stacking of wire coils as per allocated areas and FIFO system | On receiving |
|
|
| Identification tags |
| Any difficulty experienced during this activity report to Stores Coordinator |
|
| 4 | Issue wire to production. | Issuing | Raw material |
| Issue wire to production. | Verification as per buff tag Setter to measure wire diameter with vernier | Issue wire to production. | Every job as per request |
|
|
| Route card |
| Should the incorrect wire be issued to production stop process, correct and inform Stores Coordinator |
|
| 5 | Form U Wire on Zukron 3 | Forming | U Wire |
| Wire shall conform to checking fixture , wire to sit flat in fixture. No rust, Score Marks and Burrs allowed. | Visual Inspection and verification in checking fixture. First-off verification by Q.A | As per work instruction | First-off at start of production. In-process 9 parts every hour and last-off |
|
|
| Record on Electronic system |
| Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor |
|
| 6 | Form Outer Wire on Zukron 3. | Forming | Outter Wire |
| Wire shall conform to checking fixture , wire to sit flat in fixture. No rust, Score Marks and Burrs. | Visual Inspection and verification in checking fixture. First-off verification by Q.A | As per work instruction | First-off at start of production. In-process 9 parts every hour and last-off |
|
|
| Record on Electronic system |
| Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor |
|
| 7 | Transport Indivual U Wires & Outter Wires to Spot Welder. | Transport | U & Outter Wire |
| Correct handling of parts during this activity. | Visual verification. | N/A | Every order |
|
|
| N/A |
| Any difficulty experienced during this activity stop the process and report to Supervisor |
|
| 8 | Dressing and cleaning of copper tips | Copper tips | Clean tips set to correct height |
| Clean and set to correct height. Heights XXXmm top and XXXmm bottom tip which will have a gap of XXmm between the copper tips. | Measure heights with a Tape measure or Steel rule. | Heights set prior to welding Cleaning of copper tips every 2 hours | Every 2 hours |
|
|
| Record on inspection system |
| Any problem experienced during this activity report to supervisor. |
|
| 9 | Break Strength Test | Weld strength | Breaking strength |
| Conduct a chisel and hammer test (To determine weld strength) as part of first off approval. | Use a 10-15mm chisel, 1kg hammer for the test. | 1 part per batch | Every batch |
|
|
| Record on inspection system |
| If the test fails, stop and call the supervisor. |
|
| 10 | Load U Wire & Outter Wire in welding jig | Loading | Correctly loaded welding jig. |
| Correct loading of wires into the loading jig to ensure a good weld. | Visual inspection to ensure wires are touching, no gaps. Ensure all hold-down clamps are in place. | Visual inspection | Every order |
|
|
| Visual inspection. First-off in sample inspections |
| Any difficulty in loading jig, stop the process and call the supervisor. |
|
| 11 | Welding & inspection of final product | Welding | Welded product |
| Welding of product. | Product to meet drawing and customer requirements No smash welds, no miss welds, no broken welds and no bent wires. | Visual verification in checking fixture for correct fitment. | First-off at start of production. In-process 9 parts every hour and last-off |
|
|
| Record on inspection system |
| Should the inspection requirements not be correct, stop the process and inform the supervisor. |
|
| 12 | Transport welded products to stores for E - Coating | Transport | Welded products |
| Correct quantities. | Visual inspection. | As per job order | Every order |
|
|
| N/A |
| Should difficulty occur during transport inform Supervisor |
|
| 13 | Send parts for E Coating. | Transport | Uncoated parts |
| Correct E Coating as per boundary sample. | Visual inspection. | Every batch | Every order |
|
|
| N/A |
| Any difficulty report to manager. |
|
| 14 | Receive coated parts. | Receiving | Coated products |
| Correct coating on parts. Correct quantity received. | Visual inspection. | Every batch | Every order |
|
|
| N/A |
| Any issues report to Quality and Production manager |
|
| 15 | Inspection of E - Coated products. | Inspection | Coated products |
| Correct coating as per (BSQ7E447) boundary sample. No cracks. colour - black. | Visual inspection/ verification. | Every order | Every batch |
|
|
| Record on inspection system |
| Any non-conforming parts shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator |
|
| 16 | Receipt products into stock. | Receipting | Completed products |
| Correct quantity to be entered on to the stock system. | Visual verification. | Every batch | Every order |
|
|
| F.A Card. |
| Any discrepancies shall be reported to the Stores Coordinator |
|
| 17 | Dispatching of products. | Transport | Completed products |
| TBSA XXX orange dunage bins XXXX, Pack XXparts in each box. | Visual verification. | As per job order | Every order |
|
1101
|
| Delivery note / invoice |
| Any difficulty experienced during this activity report to Stores Coordinator |
|
| 18 | Layout functional inspection. | Inspection | Completed product |
| Full dimensional as per SDS and PIS. | As per customer requirements. | 1 complete product | As per schedule |
|
|
| Online audit system |
| Should the audit fail, the Production manager shall be informed immediately. |
|