Work Instruction ID:   28442  
Work Instruction Number: 1053 Revision No. 3
Old Work Instruction Number:
Description
Date Created: 11/02/2021 19:28:22 Revision Date: 08/02/2024 14:52:16
Created By: Approved By:
StockCode: WorkCentre:
Customer Stock Code:    
       
Job Observation Frequency (Months)      
       
Creator Approval Date: 08/02/2024 14:52:45 Approved Date: 08/02/2024 14:52:51
Document Status: Current    
 
Work Instruction Rows
Line No.Header RowInstruction 
1

SAFETY

Ear, hand and eye protection must be worn throughout this operation.

Be careful of pinch points and weld sparks. Keep fingers clear and eyes protected at all times when the spot welder is in operation.

Edit Delete
2

SETUP & PREPARATION

  • Ensure the spot welder set up is complete.
    • Correct program & weld settings are used - as per spot welder data parameter check sheet (QD:328/02/19).
    • Air & water flow is adequate.
    • Copper tips are dressed.
    • Copper tip heights are correct.
  • Fill in the data parameter check sheet - QD:328/02/19 before running production.

Ensure the correct wire has been issued by validating GRN buff tag against the route card.

On the production system log the time as "Setting."

Prepare a First-Off sample.

Once the first-off is correct, on the production system end the "Setting"downtime and enter the job number and operation to start the job.

Enter the first-off inspection results in the production system.

Edit Delete
3

QUALITY CHECKS

The following checks should be performed:

  • Do not force the part into the checking fixture.
  • The legs should be equal in length and line up with the CF block.
  • When placed on a flat surface the legs should sit flat (no lift).
  • Wire to sit correctly in fixture.
  • Apprearance - no burrs, rust and score marks allowed.

Examples:

 

 

 

 

 

 

 

 

 

 

 

 

Edit Delete
4

QUALITY INSPECTION

  • The Last-off from the previous batch is to be compared to the current batch's First-off. Last-off is to be placed in the production run.
  • Complete a First-off before commencing with production, and record on system Inspection.
  • First-off sample to be tagged and remain with the checking fixture - Inspection Number 6155.
  • Conduct in-process inspections every hour and record on system Inspection - Inspection Number 22575.
  • At the end of the batch, last-off part is to be tagged and kept with the checking fixture. First-off is to be placed in the production batch - Inspection Number 22576.
Edit Delete
5

REJECTS

  • All reject parts are to be placed immediatley in the red reject bins provided.
  • All rejects should be logged on the system hourly - Reject analysis no. 1016. 

Scrap / Reject bins are to be emptied at the end of end job or at the end of shift if the job is running at the end of shift

Edit Delete
6

PERFORMANCE TARGETS

Once the job has been logged on the system, you will be able to see the production figures and targets including

  • The Total Qty made against the job
  • The quantity prodcued on the shift (day),
  • The Std Time and the number of Parts required to be made per hour.

The picture to the left provides and example.

Production figures are to be logged on the system every hour.

Edit Delete